QuestionQ473
DeliveryAn agile practitioner is working on a project to migrate data from computer systems to a different location. To complete this task, four activities must be performed sequentially by different teams. The teams are migrating two systems per day, but the agile practitioner believes that three systems should be completed per day.
What can be done to improve process efficiency?
- A Use burndown charts to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.
- B Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.
- C Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.
- D Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.
Community Discussion