QuestionQ462

Mindset

During agile training, an aspiring Scrum Master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.

How should the agile trainer respond?

  • A The Kanban approach relies on storyboards.
  • B The Kanban approach focuses on adaptive, simultaneous workflows.
  • C There are no work-in-process limits in the Kanban approach.
  • D Kanban teams employ a pull system.
Explanation

Kanban teams use a pull system, in which work is selected only when capacity is available. This supports continuous flow and is commonly reinforced through work-in-process limits.