QuestionQ446
ProductA project manager has been assigned to lead development of a new application for a company. The application will be used extensively by all company employees worldwide. During the first meeting with key project stakeholders, the project manager is asked to find a way to determine every possible type of user who could interact with the application being developed.
What should the project manager do next?
- A Push it back due to the number of users and socialize the idea of developing a standard application and training session for all users.
- B Identify and create personas that can help the team better understand the needs of the target user base.
- C Build a minimum viable product (MVP), a standard application for all users, and release the new version (per users/areas).
- D Engage the human resources (HR) team to identify the key users and interview all of them accordingly.