QuestionQ441
ProductA product owner adds user stories to the backlog every day. The stories are vague requests, and the product owner expects their details to be clarified when the team works through the prioritization list.
How should team members address this challenge so that the prioritization meeting does not turn into a brainstorming session?
- A Ask the product owners to invite a subject matter expert (SME) to the meeting so the prioritization meeting will be more effective.
- B Ask the product owner to review their items with the product owner’s teammates before adding user stories to the backlog.
- C Ask the product owner to schedule a meeting with a subject matter expert (SME) to review items before adding user stories to the backlog.
- D Ask the product owner to review the stories with the scrum master before the prioritization meeting takes place.
Community Discussion