QuestionQ436
MindsetA senior manager has asked an agile team to ensure the data for burndown charts is updated in real time. However, the team is uncomfortable with this approach because it believes it is unproductive.
What should the Scrum Master do?
- A Ask the product owner to manage and share the metrics with appropriate stakeholders.
- B Meet with requestors to agree and align on reporting requirements.
- C Deny the request and explain the team's stance to the stakeholders.
- D Work with the team to create the metrics requested by the stakeholders.