QuestionQ428
DeliveryDuring Sprints, Development Team members are often invited to various meetings to provide technical opinions, which consumes the team’s working time and creates compliance issues. What action should the Scrum Master take to address this situation?
- A Request additional resources to prevent compliance issues while still fostering a collaborative workplace.
- B Escalate the concern to the product owner and request that they prioritize the development work.
- C Designate a single team member to attend the meetings and establish a capacity buffer for each sprint.
- D Reject all external meetings for the development team so they can fully focus on their sprint tasks.