QuestionQ421

Delivery

An organization uses a predictive approach for project management. Executives prefer seeing more deliverables within a short period and require milestones to be met on schedule.

What value could the organization gain from adopting an iterative approach?

  • A New tools that deliver iterative and incremental work
  • B A more predictable delivery schedule and better quality
  • C Higher levels of activity-based planning and user histories
  • D Increased focus on the value and benefits delivered
Explanation

An iterative approach delivers work in small increments and uses ongoing feedback to prioritize the most valuable outcomes. This increases focus on the value and benefits delivered, rather than primarily on completing a fixed plan and meeting predetermined milestones.