QuestionQ4

Leadership

A product owner for two highly visible projects spends substantial time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams seek clarification about the requirements and overall priorities.

What should the agile project manager do?

  • A Provide both project teams with the highest priority needs
  • B Request the project team's questions in writing prior to the next meeting
  • C Facilitate a meeting with each team and the product owner to finds a solution
  • D Provide both teams with each project's documentation
Explanation

An agile project manager should facilitate collaboration between the product owner and each delivery team to resolve requirement questions and establish priorities. This removes a communication impediment while preserving the product owner’s accountability for product decisions.