QuestionQ375
DeliveryA Scrum Master is 6 days into a 10-day iteration. A customer representative asks the Scrum Master whether they can view the most recent project update.
Which action should the Scrum Master take?
- A Share the information radiator.
- B Email the latest release plan.
- C Invite them to the next retrospective.
- D Send the latest project report.