QuestionQ375

Delivery

A Scrum Master is 6 days into a 10-day iteration. A customer representative asks the Scrum Master whether they can view the most recent project update.

Which action should the Scrum Master take?

  • A Share the information radiator.
  • B Email the latest release plan.
  • C Invite them to the next retrospective.
  • D Send the latest project report.
Explanation

An information radiator makes current project and iteration information visible and readily accessible to stakeholders, providing the requested update without waiting for a later event or preparing a separate report.