QuestionQ372

Delivery

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration-planning session, the team determines that the next highest-priority item will require more time than expected to complete during the current sprint.

What should the agile practitioner do next?

  • A Schedule a meeting with the product owner to review the sprint priorities.
  • B Put the high-priority item back into the product backlog.
  • C Extend the sprint end date to accommodate the high-priority item.
  • D Ask the project sponsor to add more resources to ensure timely completion.
Explanation

Sprint duration is fixed, and the product owner is responsible for ordering and clarifying backlog priorities. Reviewing sprint priorities with the product owner enables the team to adjust scope or select work that can realistically be completed within the sprint timebox.