QuestionQ355

Delivery

A Scrum Master is working with a team on a complex software project scheduled to last 2 years and include a series of product releases. The Scrum Master is responsible for planning the next 6 months of the project and has recommended planning the project upfront.

What should the Scrum Master do?

  • A Add the releases into a roadmap with milestones and activities.
  • B Identify dedicated tasks and activities with regular feedback loops.
  • C Deliver in small and continuous iterative releases.
  • D Identify the requirements' schedule within set time scales.
Explanation

Scrum uses an iterative, incremental approach to manage complexity, optimize predictability, and control risk. Delivering small, continuous iterative releases enables frequent inspection, feedback, and adaptation instead of relying on detailed upfront planning for a lengthy period.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!