QuestionQ328

Product

A customer is having trouble describing how the highest-priority feature will function. What should the agile project manager do?

  • A Create a time-boxed spike story to reduce the technical risk of the feature.
  • B Commence an iteration 0 for the customer and the team to investigate the feature.
  • C Facilitate the decomposition of the feature epic into more manageable user stories.
  • D Facilitate a just-in-time exploration of the functionality by the customer and the team.
Explanation

Agile teams refine requirements through ongoing collaboration with the customer or product expert, obtaining and elaborating the detail needed when it is needed. Joint, just-in-time exploration clarifies the feature’s intended functionality before committing it to implementation; a technical spike is for technical uncertainty rather than an unclear business requirement.