QuestionQ316
DeliveryStakeholders are dissatisfied because they were not consulted about the user interface (UI) for a project that will significantly affect end users after launch. How should this situation be addressed?
- A The agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.
- B The agile practitioner should inform the stakeholders that the UI has already been approved by the project team and the project sponsor, so the team is committed to staying the course.
- C All stakeholders should go through the approved project charter and the business requirements document to reduce the number of late changes or requests.
- D The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.