An agile project manager notices that the Scrum team is behind schedule in completing a particular sprint. What should the agile project manager do?

  • A Facilitate by providing directions to the team about how they can get back on track.
  • B Request key stakeholders to extend the sprint to enable the team to complete their tasks on time.
  • C Ask the customers to help the team complete the testing on time to be able to finish their tasks on time.
  • D Understand the impediments and facilitate issue resolution to enable the team to succeed.
Explanation

A Scrum Master supports the Scrum Team’s effectiveness by helping remove impediments to its progress. Facilitating resolution of the issues that are blocking the team preserves the team’s self-management and enables it to work toward the Sprint Goal.