QuestionQ310
DeliveryAn agile project manager notices that the Scrum team is behind schedule in completing a particular sprint. What should the agile project manager do?
- A Facilitate by providing directions to the team about how they can get back on track.
- B Request key stakeholders to extend the sprint to enable the team to complete their tasks on time.
- C Ask the customers to help the team complete the testing on time to be able to finish their tasks on time.
- D Understand the impediments and facilitate issue resolution to enable the team to succeed.