QuestionQ288
DeliveryAfter completing three sprints, the product owner and sponsor request an accurate schedule showing when all releases will be delivered. What should the agile practitioner do?
- A Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.
- B Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.
- C Use analogous estimating techniques based on projects with a similar velocity.
- D Provide a delivery range based on the team's estimated velocity.