QuestionQ285
DeliveryA project team is working on sprint seven of a release estimated to take twelve sprints to complete. The team has reviewed this sprint’s stories and found that rework from earlier sprints will be required.
What should the scrum master do?
- A Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.
- B Ask the team to find a workaround so that they can continue with the current project management plan.
- C Advise the team to continue working on the sprints as the release plan has been set.
- D Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.