The lead developer told the team they had learned about possible integration challenges in building customer dashboards with the architecture the team selected. What should an agile practitioner do?

  • A Conduct an architectural spike immediately to decide how the functionality will be determined.
  • B Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.
  • C Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.
  • D Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.
Explanation

Possible integration challenges with the selected architecture constitute a technical risk. The team should identify the risk, determine its response, and add and prioritize an architectural spike on the product backlog to investigate and establish a solution. Agile risk management uses a risk-adjusted backlog and risk-based or architectural spikes to reduce technical uncertainty.