QuestionQ276
ProductAfter the second retrospective with project stakeholders, the customer expresses frustration. The customer seeks a more predictable roadmap for delivering features and functionality.
How should the project manager respond to the customer?
- A Explain to the customer that an agile approach requires re-prioritization at the beginning of each sprint, so it is not possible to provide a roadmap.
- B Ask the customer to develop a roadmap the team can follow for future delivery.
- C Work with the customer to understand which user stories will deliver the best business value, re-prioritize the backlog, and share it with the customer to provide release plans.
- D Work with the product owner to develop a tentative roadmap for the customer but explain that it is always subject to change.