QuestionQ27

Delivery

A product owner believes that the last Sprint did not adequately deliver what was valuable toward the organization’s overall project goals.

What should the Scrum Master raise at the next retrospective?

  • A Solutions to project problems that were built into the last sprint
  • B Problems that arose
  • C Solutions that saved the organizations the most time and money
  • D Problems that were solved
Explanation

The Sprint Retrospective enables the Scrum Team to inspect the Sprint and identify improvements that increase quality and effectiveness. Discussing problems that arose reveals impediments and process issues that may have limited delivery of valuable work, allowing the team to plan corrective changes for future Sprints.