QuestionQ265
DeliveryDuring a project, the customer requests a requirement that clearly differs from the contract terms. How should the contractor respond?
- A Proceed with the work only after the contract is amended.
- B Discuss the value of the change for the project with the customer.
- C Evaluate effort and impact and ask for steering committee and shareholder approval.
- D Stick with the contract terms and agree to review the requirement if time allows.
Community Discussion