QuestionQ261
DeliveryAs part of an organizational change, every project team in the digital channel’s portfolio has been instructed to shift from 3-week iterations to 2-week iterations. The development team is frustrated because it believes there will not be sufficient time for testing. The product owner dislikes the change because it will increase the number of ceremonies.
Which two actions should the scrum master take?
Choose two
- A Proactively engage the resource managers to lead the team and provide the required support.
- B Request the enterprise coach and human resources support the team with the transition.
- C Document the pros and cons and review with stakeholders to determine the dependencies.
- D Protect the team from disruptions and seek an exemption for status quo.
- E Assess the impacts of the change and brainstorm potential solutions.