QuestionQ248

Delivery

The product owner is highly concerned that work may not be completed and tested before a fixed release date. What can the agile team do to mitigate this risk?

  • A High-risk features can be prioritized to fit into releases with less work in progress.
  • B Low-risk, low-value features can be prioritized and completed first.
  • C High-risk, low-value features can be evaluated by the team early in the release.
  • D The work in progress can be adjusted to get more reviews with high-risk features.
Explanation

Evaluating high-risk, low-value features early exposes technical and delivery uncertainty while time remains to adapt the release scope or avoid spending effort on work that is not worthwhile. Early investigation of the riskiest work is an agile risk-reduction practice.