QuestionQ243
DeliveryA software company is building an accounting software system to sell to customers. The team has worked on the project for six weeks and has strong velocity. A major stakeholder has approached the Scrum Master to request a bi-weekly status report because they believe they are not receiving adequate updates.
How should the Scrum Master respond to this request?
- A Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.
- B Create and update bi-weekly project status reports for the stakeholder who requested the report.
- C Escalate this to the stakeholder's supervisor because this is an unreasonable request.
- D Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.