QuestionQ215

Delivery

An agile team’s productivity declined significantly during the last sprint. Team members have not raised any impediments, but they appear fatigued.

What should the agile practitioner do?

  • A Discuss the issue with the team at the next daily standup meeting.
  • B Discuss the issue with the team at a special meeting for this purpose.
  • C Discuss the issue with the project stakeholders at a special meeting for this purpose.
  • D Discuss the issue with the team at the next project retrospective.
Explanation

A prompt, dedicated discussion with the team gives members space to identify workload, morale, or other impediments that may not surface during a brief daily standup. Addressing apparent fatigue without waiting for the next retrospective enables timely support and corrective action.