QuestionQ212
LeadershipAn agile leader is assigned to a project involving substantial technical complexity. What should the agile leader do to position the project for success?
- A Address this impediment by obtaining suitable training for the team.
- B Address the risks resulting from complexity within sprint zero.
- C Facilitate team brainstorming of the risks resulting from complexity for the risk register.
- D Motivate the team to try new technical approaches.