QuestionQ212

Leadership

An agile leader is assigned to a project involving substantial technical complexity. What should the agile leader do to position the project for success?

  • A Address this impediment by obtaining suitable training for the team.
  • B Address the risks resulting from complexity within sprint zero.
  • C Facilitate team brainstorming of the risks resulting from complexity for the risk register.
  • D Motivate the team to try new technical approaches.
Explanation

Technical complexity creates risks that should be identified collaboratively, assessed, and recorded so the team can monitor and respond to them. Facilitated team brainstorming draws on the team’s technical knowledge and supports effective risk management through the risk register.