QuestionQ199

Delivery

Question Image

Based on the chart, what is the iteration’s current status when comparing planned story points with completed story points?

  • A The iteration is in jeopardy
  • B The team has removed scope
  • C The iteration is ahead of schedule
  • D The team's velocity is constant
Explanation

The actual remaining work is higher than the planned remaining work, so progress is behind the planned trajectory. This puts the iteration at risk of not completing its planned scope on time.