DeliveryAn agile team is developing a release plan for a project.
What information does the team need to complete this plan?
- A Amount of work needed to complete a single user story
- B Amount of work that can be accomplished by each team member
- C Amount of work that can be accomplished in an iteration
- D Amount of work that can be accomplished by the entire team