QuestionQ191

Delivery

An agile team is developing a release plan for a project.

What information does the team need to complete this plan?

  • A Amount of work needed to complete a single user story
  • B Amount of work that can be accomplished by each team member
  • C Amount of work that can be accomplished in an iteration
  • D Amount of work that can be accomplished by the entire team
Explanation

Release planning uses the team’s velocity—the amount of work completed in an iteration—to forecast how much work can be delivered over the planned iterations.