Delivery

A Scrum Master belongs to a project team that uses technologies governed by the IT department. The IT director manages several company initiatives and does not know the details of each one.

As an active project stakeholder, which meeting should the IT director be invited to?

  • A Planning
  • B Daily scrum
  • C Sprint demo
  • D Retrospective
Explanation

A Sprint Review (commonly called a sprint demo) is where the Scrum Team presents the Sprint’s results to key stakeholders, discusses progress toward the Product Goal, and uses stakeholder feedback to guide future adaptations. The Daily Scrum and retrospective are primarily internal Scrum Team events, while Sprint Planning is for planning the team’s Sprint work.