A Scrum Master belongs to a project team that uses technologies governed by the IT department. The IT director manages several company initiatives and does not know the details of each one.
As an active project stakeholder, which meeting should the IT director be invited to?
APlanning
BDaily scrum
CSprint demo
DRetrospective