QuestionQ177

Product

A project sponsor is frustrated that an enhancement will not be available until next year.

What should the product owner do?

  • A Accept responsibility for the product's delay
  • B Ensure that the project sponsor's priorities are in the product backlog
  • C Negotiate with the project sponsor for increased funding
  • D Empower the project sponsor to manage the product backlog
Explanation

The product owner ensures that stakeholder priorities are captured in and considered through the product backlog. This enables the enhancement to be evaluated and ordered against other work according to product value and priorities.