QuestionQ172

Delivery

Agile Team A is having difficulty delivering its committed stories because of technical dependencies on Team B, which repeatedly does not meet its delivery commitments.

What should the agile team lead do?

  • A Create a new team to deliver the dependencies, and bring team B under performance management
  • B Conduct a vision-sharing session with the teams to communicate the project's overall goals
  • C Swap team members from both teams so that deliveries are better supported
  • D Discuss negotiating the delivery timelines with team A
Explanation

A shared vision aligns both teams around the project’s overall value and priorities, making the impact of cross-team technical dependencies visible and supporting coordinated, mutually agreed delivery commitments. Agile team leadership addresses risks and dependencies through collaboration and planning rather than command-and-control performance actions or unilateral schedule changes.

Learn more