QuestionQ136

Delivery

During an iteration-planning meeting, the team proposes changes that add product value but will require additional work and affect the schedule.

What should the agile project leader do?

  • A Re-estimate the project
  • B Finish the product as it was initially planned
  • C Try to include as many changes as possible
  • D Ask the product owner for approval to proceed
Explanation

The product owner is responsible for prioritizing product work and making value-versus-schedule trade-offs. Approval from the product owner is required before proceeding with scope changes that require extra work and affect the schedule.