QuestionQ120

Delivery

What should a team do if it achieves all Sprint Goals sooner than anticipated?

  • A Begin working on an item in the backlog
  • B Ask the scrum master to select an item from the backlog on which to work
  • C Ask the product owner to select an item from the backlog on which to work
  • D Jointly decide with the scrum master on an item from the backlog on which to work
Explanation

The Product Owner is accountable for ordering the Product Backlog to optimize product value. The appropriate additional work should therefore be selected with the Product Owner’s direction, rather than being chosen by the Scrum Master or started arbitrarily. Scrum Guide

Learn more