QuestionQ120
DeliveryWhat should a team do if it achieves all Sprint Goals sooner than anticipated?
- A Begin working on an item in the backlog
- B Ask the scrum master to select an item from the backlog on which to work
- C Ask the product owner to select an item from the backlog on which to work
- D Jointly decide with the scrum master on an item from the backlog on which to work