QuestionQ53
Supply PlanningWhich two statements are correct about Production Scheduling?
Choose two
- A Schedule options include: Configure Scope, Parameters, and View Settings.
- B Releasing a schedule can update Manufacturing Cloud work orders with revised dates, resources, release status, and work definitions.
- C Refreshing a Production Schedule means that the schedule is being recalculated.
- D A resource’s constraint mode has two choices: Relaxed and Constrained.
- E If a work order is not firm, Production Scheduling may schedule with an alternate resource.