QuestionQ30

VerifiedSection 1 – Manage Cluster, Nodes, and Features

Because of limited maintenance-window time, an administrator wants to complete LCM updates as quickly as possible.

Which action should the administrator take before starting an LCM update to minimize delays?

Explanation

LCM updates can require workloads to be live-migrated while hosts are placed into maintenance. VM affinity rules may block or restrict those migrations, delaying host evacuation and therefore the update process. Disabling the rules beforehand removes that constraint.