QuestionQ17

VerifiedInterpret and Configure Business Continuity & Disaster Recovery (BCDR) Requirements

Refer to the exhibit.

Question Image

An administrator is configuring Metro Availability in their environment, as depicted in the diagram.

Which configuration issue will prevent Metro from working correctly?

Explanation

Metro Availability requires inter-site latency below 5 ms RTT for synchronous replication. The 25 ms RTT between Site 1 and Site 2 exceeds that limit. Nutanix also specifies witness latency below 200 ms, so the depicted 200 ms witness links are a boundary ambiguity. (nutanix.com)