QuestionQ12
Manage the Microsoft Power Platform environmentYou test a business process flow in a sandbox environment.
After testing is complete, you must copy the business process flow to a production environment without carrying over any data or other changes.
You must satisfy the requirements.
What should you do?
- A Export the default solution.
- B Create a view and export the view.
- C Add the business process flow to a separate solution. Export the solution.
- D Export the form that contains the business process flow to a separate solution.
Community Discussion