QuestionQ19

Agile Testing Methods, Techniques and Tools

Iteration planning for Sprint 5 of the current project has been completed. The sprint plan is to improve system performance. Which of the following acceptance criteria would you expect for Sprint 5?

  1. User access for every role has been validated.
  2. A static-analysis tool has run against all code.
  3. 100% of the existing regression test suite has passed.
  4. The system responds in under 3 seconds, 90% of the time.
  5. A new version of Internet Explorer has been included.
Explanation

A performance-focused sprint should include a measurable response-time requirement, such as responding in less than 3 seconds 90% of the time, and regression testing to ensure the performance work has not broken existing functionality. Passing the full regression suite and meeting the response-time target directly validate those outcomes.