QuestionQ14

Agile Software Development

A calculator application is under development. The third sprint is planned to add calculator functionality for scientific calculations. Which TWO examples below are activities that would likely be managed on an agile task board for the third sprint?

i) A task to design the features planned for the following sprint.

ii) A task to perform an acceptance test for a user story.

iii) A task to automate regression tests.

iv) A task to take part in training in preparation for the fourth sprint.

v) A task to create a daily progress report for agile team members.

Explanation

An agile sprint task board represents work required to deliver the selected sprint backlog items. Acceptance testing verifies that a user story meets its acceptance criteria, and regression-test automation supports maintaining product quality as the scientific-calculation functionality is added.