QuestionQ55

VerifiedFundamental Agile Testing Principles, Practices, and Processes

Which statement correctly describes the differences between testing activities in Agile projects and traditional projects?

Explanation

In a traditional V-model, test phases are generally planned and performed sequentially in relation to the corresponding development phases. In Agile delivery, testing activities at different levels are integrated and can proceed in parallel within each iteration as the increment is developed.

Learn more

Community Discussion