Which statement about an Agile task board is correct?

  • A It provides detailed visual representation of the whole team's status.
  • B It is updated once at the end of each iteration.
  • C Only “in progress” tasks are shown on the task board.
  • D It is a detailed visual representation of the status of testing.
Explanation

An Agile task board provides a detailed visual representation of the entire team’s work status, typically showing tasks across workflow states such as not started, in progress, and completed.