QuestionQ64
VerifiedPreparing for Test AutomationYou are planning a pilot for an internally developed Test Automation solution (TAS).
Which two of the following are important steps to take during the planning process?
- a. Review your organisation’s current projects and identify which would be most suitable for piloting the TAS.
- b. Ensure that the developers will make the necessary commitment to TAS deployment activities.
- c. Run a series of training workshops for new TAS users before they are asked to use it.
- d. Develop a project plan for the pilot and reserve the necessary budget and resources for its implementation.
- e. Ask the developers to provide any missing functionality during the deployment activities.