QuestionQ57

VerifiedPreparing for Test Automation

You have evaluated a new tool that supports modelling the SUT and can subsequently generate test cases manually or automatically. You have persuaded your managers that conducting a pilot project for this tool is the best way forward. You must choose a project for the pilot. The available projects are:

  • Project A: A two-year project that is critical to the business and is currently in the requirements phase. This project is for a new e-commerce website and is mainly developed “in-house,” although the payment system is being developed and delivered by a 3rd-party provider.
  • Project B: A safety-critical application for software that drives and parks cars.
  • Project C: An upgrade to an important HR timesheet-tracking application that will be available as desktop and mobile applications. This is a one-month project developed in-house.
  • Project D: The payment system from Project A.

Which project would be BEST for the pilot?

Explanation

A pilot for a test automation solution should avoid both critical projects, where initial deployment delays could have major impact, and trivial projects, which provide little evidence that the solution will work in realistic circumstances. A bounded payment-system component provides a nontrivial, focused pilot scope without using the entire business-critical project.

Learn more