You are the TAE for an Agile project with six sprints in the current release. Sprint five is in progress, and the automated regression suite is scheduled to begin later today.

You have reviewed the automated-regression results from the previous four sprints again. You find that two test cases both passed in sprints 1 and 4, but failed in sprints 2 and 3. The failures were not detected and consequently remain unexplained. Both test cases are tightly coupled to other tests in the suite.

What action SHOULD you take?

Explanation

Intermittent, unexplained automated-test results are unreliable and require root-cause analysis. Removing the affected tests from the active regression run prevents their coupling from destabilizing or obscuring the suite’s results, while separate parallel analysis can determine whether the cause is in the test case, system under test, test automation framework, environment, or shared dependencies. The ISTQB CTAL-TAE syllabus specifies root-cause analysis for unexpected test results and recommends isolated execution as an aid to diagnosis.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!