QuestionQ31
VerifiedPreparing for Test AutomationYour company is about to begin a project to replace an old sales and merchandising system with a new version based on modern platforms. The system's main requirements are:
- Loading sales data, sent electronically from stores each evening, into a central database.
- Producing sales reports for merchandisers, whose role is to manage stock levels in stores.
- Producing forecast reports to predict future demand for each product, based on a combination of sales history and forecasting parameters. Merchandisers will enter the parameters through a browser-based front end, and the reports will be produced overnight. Users will be able to retrieve the reports, either on screen or in print, through an interactive feature.
Requirements 1 and 2 were already fulfilled by the old system and will be rewritten in the new system with minor functional changes. As before, the sales data will be loaded in an overnight batch run. The old system has experienced problems during peak periods when this run took longer than scheduled, preventing dependent jobs from completing before the next working day. The Data Centre manager requires the new system's overnight batch runs, including the new reports, to take 10% less time than the old system so that all jobs can complete.
Requirement 3 is new. The functionality provided by the UI will be simple, and the Sales & Merchandising manager requires it to be easy to use. Data for testing the reports will be extracted from the old production system and anonymized before use.
The system will be developed using an Agile lifecycle with fixed-length iterations; this will be the first full deployment of this methodology, which has just completed a successful pilot. It is a relatively simple development and is expected to be completed in three releases, each taking approximately 2 months.
You are an experienced TAE recruited to implement test automation on this project and have begun evaluating candidate tools to automate functional and some non-functional testing. It is already clear that no single tool will meet every requirement, and that the developers' existing Integrated Development Environment will meet their testing automation needs. The TAS will need to support CI/CD.
When reviewing your tool comparison table, which TWO tool capabilities will be MOST beneficial for this project?
Community Discussion