QuestionQ56

Performance Testing in the Software Lifecycle

Based on this scenario, at what time during this software and system update project is it best to analyze and assess performance risks?

Explanation

Performance-risk management is iterative throughout the software development lifecycle. Risks associated with capacity, scalability, and retaining quiz-session state must be assessed early and revisited as the requirements, architecture, implementation, and performance-test evidence develop, so mitigations can protect the requirement to maintain 99% of sessions through successful recording of the final answer.