QuestionQ12
The Tasks of the Test Analyst in the Test ProcessWhich of the following test-progress criteria would allow the business to determine a probable go-live date?
(i) Number of tests planned compared with number of tests executed
(ii) Number of outstanding high-priority defects
(iii) Test-team timesheets, showing how much effort has been dedicated to testing
(iv) Number of tests passed and number failed
(v) Number of defects identified in each development area
(vi) The rate at which defects are being identified
Community Discussion