QuestionQ94

VerifiedSecure Software Lifecycle Management

Which project management plan is most likely to guide the quantitative risk analysis process for a project operating in a matrix environment?

Explanation

The risk management plan establishes how project risks are analyzed and managed, including the approach and procedures for quantitative risk analysis. A matrix environment affects resource authority and staffing arrangements, but it does not replace the risk management plan as the governing plan for risk analysis.