You are the project manager for the GHY Project and are developing a risk response for a negative risk. You and the project team have identified a risk that the project may fail to finish on time, as management requires, because of creating the user guide for the software being developed. You have chosen to hire an external writer to meet the requirements and reduce the risk event. What type of risk response have you selected in this situation?

Explanation

Risk transference shifts ownership of a negative risk and its consequences to a third party. Hiring an external writer assigns the user-guide work, which threatens the schedule, to an outside party.