QuestionQ336

Secure Software Lifecycle Management

Fred is the project manager for the CPS project. He is working with the project team to prioritize the risks identified in the CPS project. Fred and the team are prioritizing risks for further analysis or action by assessing and combining the risks’ probability of occurrence and impact. Which process is Fred performing?

  • A Risk identification
  • B Risk Breakdown Structure creation
  • C Perform qualitative analysis
  • D Perform quantitative analysis
Explanation

Qualitative risk analysis prioritizes identified project risks for further analysis or action by evaluating and combining their probability of occurrence and impact. A probability-impact matrix is a common qualitative technique for this prioritization.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!