QuestionQ291

Secure Software Lifecycle Management

Which component of the change management system is responsible for evaluating, testing, and documenting changes made to the project scope?

  • A Project Management Information System
  • B Integrated Change Control
  • C Configuration Management System
  • D Scope Verification
Explanation

A Configuration Management System manages controlled changes to project baselines and configuration items, maintaining the associated evaluation, validation/testing, status, and documentation records. Project configuration management provides managed control of project documentation and baseline changes throughout the project life cycle.